Add an Action Step Not Related to a Milestone

Generally, an action step should be related to a milestone; however, there may be times when you need to add an action step that is not related to a milestone.

To add an action step not related to a milestone:

  1. 1 Go to the Milestones and Action Steps section of the case.
  2. 2 Find the Action Steps table.
  3. 3 Click on the add sign to the right of the Action Steps table.
  4. 4 Type the title of the action step in the Action Step field.
  5. 5 Click on the Type field to change the type of the action step (clinical or training), if necessary.

    Note: When you select Clinical, job coach trainers can see the title of the action step, but they will not be able to see the note. You should type a non-confidential title, and type any confidential information in the Note field.
  6. 6 Click on the Note field and type any relevant notes.
  7. 7 Select a target due date (hover over and click on the Target Due Date field, click on the calendar icon, and click on a date).
  8. 8 Click on Save and Close at the top of the screen.

Group Icon

Practice:
Add an Action Step Not Related to a Milestone

Complete the task listed below in the training system. When you finish, return to this training page and move to the next task.

  • Add an action step not related to a milestone. Complete the following fields:
    • Action Step
    • Type
    • Note
    • Target Due Date